June 2010
Previous page | Table of Contents | Next page
We recognize that outcomes-based measures are needed and are in the process of being developed. In the interim the following table summarizes the progress that was made against the internal audit projects contained in the multi-year audit and evaluation plan:
Progress Against Plan: Internal and External Audit
Audits Planned for this Period
16
The plan consisted of 14 audit engagements. These included six planned carry-overs from the previous year. Two new unplanned projects were added during the year:
Audits Completed during this Period
8
Of the 13 audit engagements planned for completion in 2009-10, six were carried-over from the previous fiscal year and have been completed.
The following were reviewed and recommended by EAAC, and approved by the Deputy Minister:
Carry-overs from 2008-09
Planned for 2009-10
Audit Removed
1
The joint internal audit and evaluation of the Weather Predictions program was removed as the scope was undefined. The project was not included and could not be carried out in the evaluation plan. As well, this project was to begin in Q4 of 2009-2010 and could not be carried out due to two new audit projects added during the year (i.e., Review of Separation Clearance Process, Professional Contracts).
The risks have been mitigated by the evaluation of Research and Development, Production and Monitoring and Support of Weather Predictions planned for 2010-11.
Planned Carried-Over Audits
2
Unplanned Carried-Over Audits
5
Carry-overs completed in first quarter of 2010-2011 and to be tabled with EAAC in June 2010.
Carry-overs to be completed in 2010-2011
Percentage of Plan completed
62%
Internal Audit recommendations followed up
57
Follow-up was conducted on 57 internal audit recommendations: two are at the planning stage, 16 at preparation of implementation, seven at substantial implementation, 23 fully implemented and nine obsolete.
40 percent of the 57 followed-up recommendations were implemented.
A detailed report on the status of internal audit recommendations and management actions is provided in Appendix B.
External Audits and Studies Completed in 2009–10 in which EC was included
12
Commissioner of the Environment and Sustainable Development (CESD):
Spring 2009
Fall 2009
Spring 2010
Office of the Auditor General (OAG):
Fall 2009
Spring 2010
Public Service Commission (PSC):
Spring 2009
External Audits in progress
9
CESD:
Spring 2010
Fall 2010
Spring 2011
Office of the Commissioner for Official Languages (OCOL):
Fall 2010
PSC:
Spring 2011
External Audit recommendations followed up
24
Of the 54 active recommendations, 42 have been made by the OAG/CESD, eight by the PSC and four by the OCOL.
Follow-up was conducted on 24 OAG selected recommendations from past audits: five are at the planning stage, three at preparation of implementation, and 12 at substantial implementation, three fully implemented and one obsolete.
12 percent of the 24 followed-up recommendations were implemented.
A detailed report on the status of management action plans for external audits is provided in Appendix C.
The AEB continues to coordinate activities with the Office of the Auditor General (OAG) through regular discussions with OAG/Commissioner of the Environment and Sustainable Development (CESD) representatives concerning the latter's audit work plan and its impact on the department's internal audit work plan. This year, the AEB also provided extensive consulting and support services in the development of two recent reports by the CESD, one an assessment of the Draft Federal Sustainable Development Strategy and the other, a Discussion Paper on Managing Sustainable Development.
As well, the AEB continues to build its working relationships with other external auditors such as the Public Service Commission (PSC) and the Commissioner of Official Languages (COL) that are increasing the number of audits in which the Department is included. The OCG and the OAG continue to include us in the scope of their audits, as outlined above in the Table.
The IA Policy aims to professionalize the function of internal audit across government. Accordingly, Central Agency expectations for strong professional practices and capacity building within the Branch are high and remain a priority for AEB. In keeping with these expectations, in 2009, AEB contracted with Ernst and Young to conduct an External Quality Assessment Review of our practices. This report was presented to the EAAC in July and concluded that the internal audit function (IA and Strategic Planning and Coordination) and processes generally conform to the International Standards for the Professional Practice of Internal Auditing.
An action plan was subsequently developed during the past fiscal year to address the recommendations arising from that review. Many of the following activities and accomplishments were in line with this action plan:
To reflect the changes in the revised IA Policy, the IA Division reviewed the IA Charter and included the AEB's Mission, Vision, Mandate and Values Statements. The IA Charter was reviewed by EAAC and approved by the DM.
The TB Directive on CAE, Internal Audit Plans, and Support to the Comptroller General requires the CAE to provide “annual overview assurance reporting to the Deputy Head and audit committee on the adequacy and effectiveness of departmental risk management, control and governance processes”. This overview assurance reporting will progress over time in terms of comprehensiveness and rigour and will be in addition to the reporting on individual risk-based audits.
In order to prepare for this, EC has taken the following steps and progress made to date includes:
As well, since last fiscal year, the audit engagements are moving away from compliance audits to program and performance audits that better support the annual overview assurance. The following engagements illustrate this shift:
2009-2010 Audit engagements:
2010-2011 Audit engagement:
While progress has been made in 2009-2010, further work is required and will continue in the following fiscal year to better define and develop how the branch will be providing annual assurance.
To strengthen reporting and accountability for implementation of recommendations, the Branch has developed a common approach for the development of management action plans for individual audits, both internal and external, and for overall reporting on the status of implementation of recommendations. The EAAC has noted the progress made by the department with regards to the quality of management responses and action plans as a result of the efforts of the Branch.
Follow-up processes have been enhanced and regular reporting to senior management of the status of past recommendations has been improved. These new procedures provide senior management and the EAAC with comprehensive information on the status of implementation of management action plans and implementation of recommendations. All internal audit follow-up recommendations have been transferred to TeamMate, an audit software application. Evidence is analysed and documented in the software to track progress on implementing recommendations on a more timely basis (in accordance with management actions plans). The new software is in place and is ready to be used in 2010-11. Follow-up on recommendations are conducted on an ongoing basis to ascertain the degree to which the action plans in response to recommendations made in previous audits have been implemented, and to determine outstanding gaps/risks. Progress reports on follow-ups are provided on a regular basis to the EAAC, the Executive Management Committee and the Deputy Minister. A detailed report on the status of internal audit recommendations and management actions at year end is provided in Appendix B.
After each audit, the IA Division sends surveys to clients in order to assess internal audit products and services. Managers are asked to provide feedback on the quality of the internal audit products and services. The Assistant Deputy Ministers (ADMs) responsible for the function that was audited are asked about the value of the audit. During this year, the IA Division sent out surveys for three audits (Efficiency of staffing operations, Occupational Health and Safety and Costing and Pricing Processes for Revenue Generation). The Division received responses from ADMs and managers for two audits. One included positive comments about the value of the audit and the quality of audit services provided while the other indicated some concern over the audit process. Survey results and the corresponding lessons learned are being used as part of the continuous improvement process.
One of the hallmarks of the internal audit profession is the commitment to quality assurance and review. During previous reporting periods both internal and external quality assurance reviews identified some opportunities for improvement. Efforts to address these findings have been undertaken.
As part of the AEB Quality Assurance Program, the IA and Strategic Planning and Coordination (SPC) Divisions conduct an annual internal quality assessment (IQA) against the Institute of Internal Auditor (IIA) Standards and Policy on Internal Audit. The January 2010 IQA conducted (using the updated Internal Audit Quality Assessment Tool which reflects all changes to the Policy on Internal Audit and the IIA International Professional Practices Framework (IPPF)), confirmed that the IA (both IA and SPC) function is in general compliance.
As previously noted, an External Quality Assessment was conducted in May 2009 and the results presented to EAAC. The Assessment found that there was general compliance with relevant standards. The Assessment did identify two areas of partial compliance and made a number of recommendations. The areas of partial compliance concerned planning and follow-up which have been addressed. A detailed action plan was developed to address the recommendations and was presented to EAAC in June 2009. Progress on the action plan is presented to the EAAC at every meeting. Most actions had been completed by January 2010.
A number of important themes developed over the course of the past year as a result of the Branch's activities and can be treated as relevant lessons learned going forward. These lessons will be responded to through future audit plans and activities and are presented here, at a high level, for broad consideration.
Lessons Learned by Internal Audit relevant to the overall Department:
Lessons Learned by Internal Audit relevant to the AEB:
Lessons Learned from External Audit relevant to the AEB:
In addition to the themes identified for internal audit, lessons learned that pertain to both the Audit and Evaluation Branch's management of, as well as the department's participation in, external audits are: