
| TOC | Previous | Next |
Appendix 6.10 Noranda Metallurgy Inc.,Horne Smelter, Rouyn-Noranda, Quebec
Profile
Noranda Metallurgy Inc., Horne Smelter, operates a copper smelter in Rouyn-Noranda,
Quebec. The plant started production in 1927 to process copper concentrates
produced by an associated mine-mill complex. Prior to the 1970s, the smelter utilized
conventional copper smelting technology including reverberatory furnaces and Peirce-Smith
converters. Development and installation of Noranda's patented reactor for the
treatment of copper concentrates permitted the gradual elimination of the reverberatory
furnaces. The mine closed in 1976, and the smelter now processes custom and toll
copper concentrates and secondary materials from a variety of sources world-wide. A
sulphuric acid plant entered service in 1989. The smelter produces copper anodes
and sulphuric acid. Selected production data for the period 1988 to 1995 are
presented in Table A6.10.1, which includes projected levels for the year 2000.
Table A6.10.1 Production Summary (tonnes)
| 180,000 |
195,000 |
213,000 |
205,000 |
| 0 |
407,000 |
416,000 |
510,000 |

Process Description
The process is outlined in Figure A6.10.1.
Figure A6.10.1 Noranda Horne Copper Smelter Process Flow Sheet
Click to view full version.
Copper concentrates and fluxing materials (silica) are proportioned to form a low
viscosity FeO-SiO2 slag with low copper content. New feed is mixed with recycled slag
concentrate and dust from the smelter and processed in a single Noranda Reactor.
Most of the copper in the smelter feed are contained in sulphide minerals and reports to
the molten sulphide matte phase, while the bulk of the non-sulphide gangue forms an
oxide slag containing copper at low, but economically recoverable concentrations. The
higher density matte separates from the slag, which is combined with converter slag
and is slowly cooled, ground and processed by flotation to recover most of the
contained copper. Off-gases from the Noranda Reactor are treated by a dry
electrostatic precipitator to remove particulate matter. The clean reactor off-gases are
then directed to a single absorption sulphuric acid plant for recovery of sulphur dioxide.
Dust is returned to the reactor for recovery of copper and is also bled from the circuit to
control impurity levels and reduce emissions. The gas cleaning section of the acid
plant includes a mercury tower to minimize mercury emissions and ensure acid quality.
Weak acid solution from the acid plant is neutralized with lime and mixed to react with a
ferric sulphate solution to precipitate metals in solution, combined with mill tailings from
slag flotation and co-deposited in the tailings impoundment area.
Matte is processed on a batch basis in Peirce-Smith converters to oxidize sulphur to
sulphur dioxide and reduce copper to the metallic state. Oxygen-enriched air is used to
convert iron sulphide to iron oxide, which combines with added flux to form an oxide
slag and separates from the copper sulphide matte phase. This slag contains relatively
high copper levels and is processed together with the slag from the Noranda Reactor to
produce a slag concentrate that is returned to the reactor. As the converter cycle
continues, copper sulphide is converted to blister copper containing dissolved sulphur
and oxygen. Conversion of iron and copper sulphides produces converter off-gases
containing substantial quantities of sulphur dioxide at concentrations which vary over
the course of the batch operation. Converter off-gases are treated by a dry
electrostatic precipitator to remove particulate matter. Dust is returned to the reactor
for the recovery of copper, and is also bled from the circuit to control impurity levels
and reduce emissions. The cleaned converter off-gases are released to the
atmosphere. A portion of the copper concentrate feed is dried and injected directly into
the Peirce-Smith converters to supplement the matte feed and maintain production
capacity since the shutdown of the reverberatory furnaces.
The dust bleed stream containing copper, lead, cadmium, arsenic and other impurities
is processed to recover valuable metals and then stabilized at the site. Effluents from
dust treatment are treated by lime neutralization and ferric sulphate at the weak acid
treatment plant, combined with mill tailings from slag flotation, and codeposited in the
tailings impoundment area.
Blister copper is processed in an anode refining furnace to remove most of the
dissolved oxygen and sulphur. The product is then casted into copper anodes, which
are shipped to Noranda Metallurgy Inc.'s CCR Refinery in Montreal-East for electrolytic
refining of copper and precious metals.

Releases
Point sources of releases to air and water from the smelter are shown in Figure A6.10.1
and controlled as outlined above.
Dry process gases from the Noranda Reactor and converters are treated by dry
electrostatic precipitators for particulate control. Process gases from the reactor are
treated and cleaned through a single absorption acid plant. Process gases from the
converters containing lower concentrations of sulphur dioxide are not strong enough or
consistent enough in strength to be sent to an acid plant and are released to the atmosphere. These controls maintain vessels under negative pressure and reduce
fugitive emissions from process equipment. All conveyors are fully enclosed to reduce
fugitive emissions.
Major liquid effluents from the smelter site are collected and treated at the weak acid
water treatment plant, combined with slag flotation concentrate tailings and are
monitored. Other effluents are lime treated along with acid mine drainage from old
sulphide mine tailings and are sent to polishing ponds and monitored.
Selected release data for the period 1988 to 1995 are presented in Table A6.10.2 and
Figure A6.10.2 and projected levels for the year 2000 are included. Releases of CEPA
substances decreased by over 60% from 1988 to 1995 and further release reductions
are projected.
Table A6.10.2 Releases to Air and Water and Off-site Transfers
by Noranda Horne, Rouyn-Noranda, Quebec (tonnes) (Cu Smelter)
| 113.0 |
23.0 |
34.5 |
25.0 |
| |
2.4 |
0.6 |
0.7 |
| 113.0 |
25.4 |
35.1 |
25.7 |
| |
0.0 |
0.0 |
0.0 |
| 39.0 |
5.4 |
3.9 |
6.0 |
| 0.4 |
0.1 |
0.1 |
0.1 |
| 39.4 |
5.5 |
4.0 |
6.1 |
| |
0.0 |
0.0 |
0.0 |
| 850.0 |
215.7 |
355.0 |
250.0 |
| 1.4 |
1.1 |
0.6 |
1.0 |
| 851.4 |
216.8 |
355.6 |
251.0 |
| |
0.0 |
0.0 |
0.0 |
| 1.70 |
0.00 |
0.30 |
0.40 |
| 0.00 |
0.00 |
0.00 |
0.00 |
| 1.70 |
0.00 |
0.30 |
0.40 |
| |
0.00 |
0.00 |
0.00 |
| 0.0 |
0.7 |
1.5 |
3.0 |
| |
1.1 |
0.6 |
0.7 |
| 0.0 |
1.8 |
2.1 |
3.7 |
| |
0.0 |
0.0 |
0.0 |
Figure A6.10.2 Noranda Horne Releases to Air and Water
Click to view full version.
Click to view full version.
Click to view full version.
Some potential to form dioxins and furans exists at smelters with chlorinated plastics or
other chlorinated substances in their feeds. Mechanical pretreatment can effectively
separate metals and plastics contained in wire, but cannot separate copper from
printed circuit boards or other electronic scrap. These particular materials constitute an
important feed source for the Horne smelter.
This risk was anticipated by Noranda and Québec. Such materials are smelted only in
the Noranda Reactor, and reactor off-gases are processed by an acid plant.
Combustion parameters exceed design criteria established to minimize dioxin and furan
releases from hazardous waste incinerators. Detailed and comprehensive sampling
and analysis was conducted by or in the presence of provincial officials to verify
performance over a wide range of operating conditions. Acid plant tail gas, weak acid
and the intermediate and final effluents from the tailings pond were sampled and
analysed for organic parameters selected by Québec, with the methodology based on
methods published by the U.S. Environmental Protection Agency. An international
toxic equivalent factor was used to express the results in terms of Toxic Equivalent 2, 3,
7, 8 PCDD/PCDF by calculation according to a method published by the North Atlantic
Treaty Organisation. During the test periods, recyclable feed rates were as high as 64
t/h, exceeding the usual feed rate of 12 t/h by a factor of four to five. The results
demonstrated that even at exceptionally high plastics feed rates, combined releases to
air and water from the smelter would not exceed 0.1 g/y.

Regulatory and Non-Regulatory Programs
The copper smelter is regulated by the Quebec Ministry of Environment and Wildlife
(MEF). An SO2 emission standard of 276,000 tonnes/y (50% of the 1980 level) was
implemented by regulation and came into force for 1990, triggering construction of an
acid plant at the end of the 80's. Current emissions are around 165,000 tonnes/y SO2.
Québec has also established a particulate emission standard of 50 mg/m3 for
ventilation sources associated with concentrate handling. Certificates of authorization are
required for installation of controls on air emissions (such as baghouses, etc.). The air
quality regulations are under review and may be amended to further limit SO2
emissions to levels consistent with Noranda's public commitments. The smelter has
committed to limit SO2 emissions to 30% of the sulphur input and particulate emissions
to 1.2 kg/t (feed basis) by 1998 and to reduce those emissions to 10% of input sulphur
and 0.4 kg/t (feed basis), respectively, by 2002.
Québec has also established ambient SO2 air quality standards for hourly, daily and
annual averaging periods. The current standard for the hourly mean concentration is
0.50 ppm. The regulation under review would reduce the standard to 0.34 ppm but
would allow for exceedances of not more than 0.20% of the total sampling hours
provided that the concentration does not exceed 0.50 ppm.
The smelter effluent is subject to the general prohibition of deposits of deleterious
substances in Subsection 36(3) of the Fisheries Act. Liquid effluents are controlled by
the Quebec Ministry of Environment and Wildlife through Directive 019. A separate
certificate of authorization covers the liquid effluent from the tailings pond, which
receives treated water from the weak acid treatment plant.
Noranda accepted the ARET challenge in 1994 and submitted an action plan that
detailed specific goals for each substance. Noranda's goals were reviewed and
updated in mid-1996 and reported to ARET.

Monitoring and Research
The ambient air sampling network includes seven continuous SO2 monitors, linked to
the Intermittent Control System (I.C.S.). Introduced in 1971, the I.C.S. is operated by
meteorologists and technicians for predictive control of sulphur dioxide concentrations
in ambient air at ground level. Specialized scientific instruments are used to determine
atmospheric conditions and stability, which affect gaseous distribution. These
parameters are used to develop local meteorological forecasts and to predict future air
quality. Weather conditions effectively determine the allowable SO2 emission rate to
the atmosphere and smelter production levels. An environmental policy clearly
indicates the full commitment of smelter operations to comply with instructions from
I.C.S. staff concerning smelter production levels and SO2 emissions. Actual
observations recorded at the SO2 monitors confirm that the ambient air standards are
not exceeded and can also be used to refine the predictive model. In the event of an
exceedance, I.C.S. staff provide instructions to further reduce SO2 emission rates.
The ICS was modernized and installed in a new building at the restored and
revegetated Chadbourne mine site in 1990 at a cost of $1.3 million, where it provides
staff with a clear view of operations, plume movement and direction in addition to
continuous surveillance of ambient SO2 concentrations.
Dust-falls and high volume samplers are operated for particulate monitoring.
During the period 1991 to 1993, the smelter participated in a pilot project with the
Québec - MEF for evaluation of the Programme réduction des rejets industriels
(P.R.R.I.) (Industrial Waste Reduction Program). In depth characterisation was
performed for process emissions to air and water at a cost of approximately $250,000.
The Centre de technologie Noranda sampled water and sediment quality in various
lakes around Rouyn-Noranda at the end of 1994. Comparison with the results of
previous studies shows general improvements in water quality, while metal
concentration in sediments stayed at the same level. Recent release reductions are
not apparent in sediments due to the slow rate of deposition of new sediments.

Programs and Plans
1984 Constructed facilities to receive, sample and prepare recyclable materials
for processing at a cost of $X million.
1987-89 Shut down last reverberatory furnace and commissioned sulphuric acid
plant at a cost of $160 million, achieving reductions in particulate and SO2
emissions in excess of 50% for 1990 compared to 1980.
1990 Commissioned systems for concentrate drying and injection to the
converters to replace lost production capacity at a cost of $15 million.
1990-1996 Unused sections of the plant were demolished and a program of gradual
revegetation with grasses and trees was implemented around the smelter.
Demolition of Stack No. 3 was completed in 1993 at a cost of $750,000.
Annual costs are approximately $500,000 for demolition and $200,000 for
revegetation.
1991 Developed technical options for further reductions in SO2 and particulate
emissions.
Publicly committed to further reduce SO2 emissions (aiming at 90%
reduction compared to 1980).
1991-92 Worked in partnership with representatives of the community, ministére
de l'Environnement et de la Faune, municipality and regional health
services centre to initiate and complete a community program for removal
of lead-contaminated soil from the Quartier Notre-Dame, a residential
area adjacent to the smelter. Close to 650 lots were remedied by
replacing top soil and lawns at a cost of $3.1 million.
1992-93 Developed, pilot tested and implemented Peirce-Smith converter
modifications at a cost of $10 million.
1994 Constructed major in-door copper concentrate storage area at a cost of
$6 million.
Commissioned mercury removal towers in the gas cleaning section of the
acid plant at a cost of $2 million.
1994-95 Developed conceptual design of a new pyro-metallurgical vessel at a cost
of $1.9 million to reduce Peirce-Smith converter SO2 and particulate
emissions by processing reactor matte and directing off-gases to the
existing acid plant.
1996 Commenced Noranda Reactor building expansion and construction of a
Noranda converter to replace existing Peirce-Smith converter technology
at a cost of $53.3 million.
1997 Baghouse installation for particulate removal from secondary ventilation
gases from the tapholes of the Noranda Reactor and future Noranda
Converter at a cost of $2.9 million.
Noranda Environmental Awareness Training (NEAT) Program to be
offered to all employees at the Horne smelter, focused on personal
responsibility for environmental compliance and performance
improvement.
1997-98 Commissioning of the Noranda Converter to initially process 40% of
reactor matte, with the remainder being treated by the Peirce-Smith
converter. One or two Peirce-Smith converters will be modified as
refining furnaces to complete sulphur oxidation prior to the anode furnace.
Sulphur fixation is expected to exceed 70%.
1998-2001 Adaptation of operations to the new process, with Noranda Converter
throughput increasing to 100% of reactor matte. Expansion of some
sections of the sulphuric acid plant to process all reactor and converter
off-gases at a cost of $50 million. Sulphur fixation is expected to exceed
90% by 2002.

Issues
Commissioning of the Noranda Converter entails substantial technical and financial
risks, since new metallurgical principles will be applied in this vessel. This proprietary
technology was developed by Noranda and the Horne installation will be the first
commercial application.
Custom smelting brings uncertainty in the long term supply of feed materials. A
successful custom smelter must have the capability to efficiently process feeds of
varying quality while maintaining consistent product quality and competitive operating
costs and concentrate treatment charges.
Capital resources will be scarce within Noranda Metallurgy Inc. for the next several
years as major investments are foreseen at the Horne, C.C.R. and C.E.Z. and for
potential development of the Magnola project to recover magnesium from asbestos
residues.

Technical Options to Achieve Further Release Reductions
An Environment Canada report for the Acidifying Emissions Task Group characterizes
the Horne as a large size copper smelter with an acid plant. From a national
perspective, SO2 emissions remain major at this site in spite of substantial reductions to
date. Noranda's current plans will increase the capture of SO2 to 90% and will also
achieve further reductions in metal emissions. When those plans have been
implemented, the facility will employ current state-of-the-art process and pollution
control technology and management practices and will have no significant uncontrolled
sources of metal releases. Further incremental release reductions beyond the year
2002 could be achievable with continual improvement.

|